Project Update Memo #3
Dear Unit Owners,
We would like to provide an update on the progress of the bulkhead replacement project at the Island at Hidden Harbour.
Over the past two months, despite several weather-related challenges, the construction crew has made significant progress. To date, the team has successfully installed all the new vinyl sheeting for the bulkhead, disconnected and re-routed the necessary electrical and plumbing lines, and installed both the upper and lower whalers. In addition, the crew has begun the required excavation of the tie-back rods.
Over the next few weeks, work will focus on welding new rods to the existing tiebacks to ensure the bulkhead wall is properly reinforced and supported. Once this work is complete, the area will be backfilled behind the new bulkhead. Following the backfilling phase, construction of the new boardwalk structure and installation of the decking will begin.
We would like to acknowledge the hard work and dedication of the construction crew. They have worked through multiple weather obstacles to keep the project moving forward and on schedule.
Currently, the project has a tentative substantial completion date of April 10th, assuming continued progress and favorable weather conditions.
Thank you for your patience and support while this important infrastructure improvement is underway. Please continue to use caution when onsite and be aware of the ongoing construction work. We will continue to keep the community informed as the project progresses.
Sincerely,
Island at Hidden Harbour Condominium Association
C/O Mana-Jit Property Management
Mana-Jit
Property Management
Property Manager: John F. Jensen, Jr
Hours: 9am - 4pm Mon - Fri
24/7 Fire or Flood Emergency Only