by Paul Bianco | May 8, 2026 | Bulkhead, Island News, Projects
Project Update Memo #4 Dear Unit Owners, We are pleased to share another progress update on the bulkhead replacement project at the Island at Hidden Harbour. All tieback rod excavation, welding, and testing has now been completed successfully. Following this work, all... by Paul Bianco | May 8, 2026 | Bulkhead, Island News, Projects
Project Update Memo #3 Dear Unit Owners, We would like to provide an update on the progress of the bulkhead replacement project at the Island at Hidden Harbour. Over the past two months, despite several weather-related challenges, the construction crew has made... by Carol Bianco | Dec 12, 2025 | Bulkhead, Island News, Projects
Bulkhead Update Memo 2 at Hidden Harbour Owners, At this time, the Board is happy to announce that the bulkhead project is under contract with Bay Coastal Marine Construction. A pre-construction walk through was completedrecently and we wanted to provide the... by Carol Bianco | Oct 31, 2025 | Bulkhead, Island News, Projects
Bulkhead Project Memo #1 Island at Hidden Harbour Owners, As discussed at the 2025 annual owners meeting, the Board of Directors has been working to develop and execute the contract for the bulkhead replacement project. Phase1 of the project is tentatively scheduled... by Carol Bianco | Nov 7, 2024 | Island News, Meeting Minutes
Reminder, the Island condo dues for 2025 will remain the same ($540/month). Payment details are included in the attached documents along with all pertinent information from the 2024 Owner Meeting. Owner Meeting cover letter – 2024 Owner Meeting Minutes –... by Carol Bianco | Oct 11, 2023 | Island News
The key takeaways from the 2023 Island Owner Meeting are: With the the adoption of the Proposed budget, the 2024 condo dues WILL INCREASE to $540 per month. This increase is primarily due to an insurance industry spike in premiums for “properties near...